Plans : Summary |
Page 17 |
Entry |
PSE requirements for entry. Complete entry requirements and implementation by 8/31/99. |
A complete list of middle tier services to be specified by 9/1/99. |
State information will be specified by 8/15/99. |
Storage and retrieval of state information discussion is to be scheduled. |
The PSE navigator will link to PSE components. There are many technical issues to resolve. Target is 8/31/99. |
Problem Description |
Tools to develop and maintain problem description supporting material. Initial object specification 8/15/99 and tools available 9/15/99. |
The current framework of the Problem Descriptor for CCM is available 9/15/99 and a compilation of discussions with other CTA's is available 9/30. |
The problem to codes and code to resources is under discussion. (TBD) |
The development of tools to provide the mappings above. (TBD) |