Foil 9 FY00 Program Plan Timetable

From Team B C G Marching Orders from Alliance Vision Team B C G Meeting Argonne -- February 1 2 1999. by Dan Reed(illinois), Rick Stevens (Argonne)


FY99 Development schedule March 1st
Draft technical roadmaps by April 1st
Program plan writing assignments April 1st
Roadmaps completed by May 1st
First draft program plan sections May 1st
Final program plan drafts by June 1st
Alliance 99 Meeting ~ PPRP ~ Sept 1st