Replied: Fri, 23 Feb 1996 13:29:17 -0500 Replied: gcf@boss Replied: furm@npac.syr.edu (Wojtek Furmanski) Replied: gene@npac.syr.edu Replied: edlipson@mailbox.syr.edu Replied: gcf@npac.syr.edu Replied: roman@npac.syr.edu Received: from by spica.npac.syr.edu (4.1/I-1.98K) id AB00767; Fri, 23 Feb 96 12:38:04 EST From: furm@npac.syr.edu (Wojtek Furmanski) Received: (furm@localhost) by king.npac.syr.edu (8.6.7/8.6.6) id KAA01757; Fri, 23 Feb 1996 10:07:44 -0500 Date: Fri, 23 Feb 1996 10:07:44 -0500 Message-Id: <199602231507.KAA01757@king.npac.syr.edu> To: gene@npac.syr.edu Subject: JoJo schedule Cc: edlipson@mailbox.syr.edu, furm@npac.syr.edu, gcf@npac.syr.edu, roman@npac.syr.edu I mean 'start end of Jan' - see his schedule. He sticks to it and in the last message yesterday he says he starts implementing abstract classes but will not send us any partial results until he knows the project is funded. thanks

Schedule

The schedule below is a rough guess at how to achieve prototype functionality required for the physical therapy application. Items shown are what it to be accomplished in each part-time week (2-3 days of work).
  1. Week of Jan 29: Project documentation, design of Neat Tools Modules (this set of HTML files)
  2. Week of Feb 5: User interface and Run time environment design.
  3. Week of Feb 12: Code generator design.
  4. Week of Feb 19: Implement abstract base classes and code generation templates
  5. Week of Feb 26: Implement code generators
  6. Week of Mar 4: Implement selected modules using code generators.
  7. Week of Mar 11: Implement visual interface, generic portion.
  8. Week of Mar 18: Implement visual interface, NeatTools specific.
  9. Week of Mar 25: Saving, Loading, Running a program.
  10. There are really two parallel efforts here, so the dependency ordered lists are really: 1,3,4,5,6 and 2,7,8,9.

    NOTE: Item 7 has been inserted as of Feb 5, due to need to maintain interface consistency with and share code with WebFlow.