Schedule
The schedule below is a rough guess at how to achieve prototype functionality required
for the physical therapy application. Items shown are what it to be accomplished in
each part-time week (2-3 days of work).
- Week of Jan 29: Project documentation, design of Neat Tools Modules (this set of HTML files)
- Week of Feb 5: User interface and Run time environment design.
- Week of Feb 12: Code generator design.
- Week of Feb 19: Implement abstract base classes and code generation templates
- Week of Feb 26: Implement code generators
- Week of Mar 4: Implement selected modules using code generators.
- Week of Mar 11: Revised user interface
- Week of Mar 18: Revised user interface.
- Week of Mar 25: Saving, Loading, Running a program.
NOTE: Items 7 & 8 inserted due to feedback on user interface meeting with Dave Warner March 7.
Sockets modules have not yet been implemented.