Project Information

Discipline
Computer Science (401) 
Orientation
Research 
Abstract

The mission of the TeraGrid Quality Assurance (QA) working group is to identify and implement ways in which TeraGrid software components/services and production deployments can be improved to reduce the number of failures requiring operator intervention that are encountered at TeraGrid resource provider sites. The TeraGrid QA group utilized FutureGrid in the below experiments: GRAM 5 scalability testing, and GridFTP 5 testing.

Intellectual Merit

Shows FutureGrid as a testbed for sophisticated distributed system middleware testing

Broader Impacts

Tested new TeraGrid middleware; illustrated how to use FG as a testbed for middleware testing.

Project Contact

Project Lead
Shava Smallen (ssmallen) 
Project Manager
Shava Smallen (ssmallen) 

Resource Requirements

Hardware Systems
  • alamo (Dell optiplex at TACC)
  • foxtrot (IBM iDataPlex at UF)
  • hotel (IBM iDataPlex at U Chicago)
  • sierra (IBM iDataPlex at SDSC)
 
Use of FutureGrid

For middleware testbed

Scale of Use

UF Nimbus cluster

Project Timeline

Submitted
07/01/2010 - 12:00 
Completed
12/31/2010